April 19th, 2019:
Project is substantially complete, the Contractor will be completing punch list items. No further road closures are anticipated.
The road repair the roadway due to the spring 2018 high water.
Schedule
Design, Permitting, Approvals: Fall 2018
Construction: Fall 2018-Spring 2019, currently scheudled with County crews and contractor assistance.
Description
Elevated runnoff in the Shields Valley in the spring of 2018 resulted in channel migration of the Shields River upstream of the Fiddle Creek Road crossing which ultimately resulted in significant lost off road section requiring closure of the roadway.
Temporary repairs were completed when the high water receeded and conditions stabilzied allowing the road to reopen.
Funding
Funding for this project is sourced from the Road & Bridge operation funds and from the Emergency & Disaster Fund 2260. Currently additional funding sources are being sought.