Tom Miner Creek Road Capital Improvements Project

Final Update June 21, 2019   Project Newsletter

Update June 14, 2019   Project Newsletter

Update June 4, 2019   Project Newsletter

Update December 20, 2018 Click for Project Newsletter  

Update December 7, 2018 Click for Project Newsletter

Update November 30, 2018 Click for Project Newsletter

Update November 16, 2018 Click for Project Newsletter

Update November 9, 2018 Click for Project Newsletter

Update November 2, 2018 Click for Project Newsletter

Update October 26, 2018 Click for Project Newsletter

Update October 19, 2018 Click for Project Newsletter

Update October 13, 2018 Click for Project Newsletter

Update October 5, 2018 Click for Project Newsletter 

Update September 28, 2018 Click for Project Newsletter

Update September 21, 2018 Click for Project Newsletter

Update September 16th, Click for Project Newsletter

Update September 7th, Click for Project Newsletter

Update August 31st, 2018: Click for Project Newsletter

Update August 24th, 2018: Click for Project Newsletter

Update August 17th, 2018: Click for Project Newsletter

Update August 10th, 2018: Click for Project Newslette

**** There will be a public information meeting regarding the project next Wednesday, August 15th at 5:30 p.m. in the Emigrant Town Hall. Members of the public are encouraged to attend to get an update on the status of the project and to have questions answered.*****

Update August 3rd, 2018: Click for the Project Newsletter

Update July 27th, 2018: Click for the Project Newsletter

Update July 20th, 2018:  Click for the Project Newsletter

Update July 13th, 2018:  Click for the Project Newsletter

Update July 6th, 2018:  Click for the Project Newsletter

Update June 29nd, 2018: Click for the Project Newsletter

Update June 22nd, 2018:    Click for the Project Newsletter

Update June 11th, 2018:     Click for the Project Newsletter

Update June 8th, 2018:      Click for the Project Newsletter

Update May 28th, 2018:      Click for the Project Newsletter

Update May 21st, 2018:    Click for the Project Newsletter

Update May 14th, 2018:   Click for the Project Newsletter

Update May 7th, 2018:      Click for the Project Newsletter

Update April 30th, 2018:   Click for the Project Newsletter

Update April 10th, 2018:   The Tom Miner Creek Road Capital Improvements Project Notice to Proceed was issued for today.  Pre-Construction work in the upcoming weeks includes survey, erosion control installation and tree & brush removal.  More information will be distributed as construction schedules are approved.  Please note the two (2) weeks notice will be provided for any detours or closures.

Update March 6th, 2018:     The Tom Miner Creek Road Capital Improvements Project solicitation is complete and and contracting for the project is in progress.  Construction remains on schedule to begin in the Spring 2018.  More information will be distributed as construction schedules are approved. 

Update November 6th, 2017:     The Tom Miner Creek Road Capital Improvements Project is currently out for solicitation through December 6th, 2017 on the FedBizOpps.gov website. Please see the following link for more information. Link

Update August 2nd, 2017: WFLHD and Park County completed the 95% Review in July 2018 along with acquiring temporary construction easements for the project.  Coordination activities are underway with the utility companies in preparation for project construction. Solicitation is scheduled for Fall 2017 and project construction remains on schedule for spring of 2018.  The scope of work for the Carbella Bridge has been modified to include deck replacement along with the already programed repairs. 

Update June 12th, 2017:  Coordination activities are underway with power and communication utility companies in preparation for the project construction, which remains on schedule for the spring of 2018.  Park County is currently working with adjacent landowners for temporary construction easement agreements.   FHWA issued a Categorical Exclusion NEPA determination for the project and completed 70% Design Review in mid-April 2017.   

Portions of this project – including the Tom Miner Bridge, 30 NBI rating - were prioritized in the 2012 Park County Capital Improvements Bridge Plan.  The Tom Miner Creek Bridge is experiencing significant undermining of the abutments and does not meet current standards for lane widths and barrier protection and conveyance.  The historic Carbella Bridge is not structurally deficient but has significant approach and departure deficiencies that result in a 41.3 NBI rating.  Rock Creek (South) Bridge, 37.5 NBI rating, provides the only alternative access to Tom Miner Creek Road and basin area for highway loads, as well as the only alternative detour to the area if the Carbella Bridge is closed.  Rock Creek (South) Bridge has the following deficiencies – failure of southwest wingwall/abutment which is anchored with steel cables under the roadway; vertical fracture in the northwest wingwall; erosion between the roadway and northeast abutment; and, undermined abutments on the entire south side and the northwest side.  Tom Miner Creek Road/Old Yellowstone Trail Road is comprised of gravel surfacing and has an estimated SADT of 244 and is maintained by Park County for the first six miles.  The remaining 5.5 miles to the Tom Miner Campground area and trailheads are maintained by the United States Forest Service.  

The project will improve access to the areas served by Tom Miner Creek Road and Old Yellowstone Trail South Road, both of which traverse near, to and through Custer Gallatin National Forest and the Tom Creek Basin area – with several tributaries flowing into the Yellowstone River.  Primary project activities will include bridge rehabilitation, approach and departure improvements, bridge replacement, minor ditch reconstruction and surfacing improvements.  Park County is able to provide a 13.42% cash and in-kind match for the project.

.

For more information regarding the Tom Miner Creek Road Capital Improvements project, please contact:


Parks Frady, Public Works Director
414 E. Callender Street Livingston, MT 59047
406-222-4114

Or:

Email any project related questions or comments to: 

Looking for something?